KEY INFORMATION
We are pleased to have reached practical completion on the complete re-wire of De La Salle College in Dundalk.
With only 8weeks available over the summer, we undertook this mammoth task to completely re-wire this 35 Classroom Secondary School
As we completely stripped out the existing services, we were also responsible for all builders works, which included removing ceilings, all making good works and external trenching and tarmacing to link multiple buildings. This project was no easy feat.
- Providing a full new electrical installation
- Complete new containment systems
- New switchboards
- All new lighting
- Power
- Data Cabling
- Fire & Security Systems
Lead on the ground by Supervisor Barney McDowell, a team of 40 Electricians, apprentices, painters, joiners and civil teams worked long hours to deliver the works.
Covering all types of teaching spaces, Technology, Science, Home economics etc, we protected the schools contents and provided a fully cleaned building at the end.
We were able to deliver the school snag free and on time to allow the return of kids for the new school year.